Owning a GB300 NVL72 rack

72 Blackwell Ultra GPUs and 36 Grace CPUs in one liquid-cooled rack. Here’s what owning one takes, and when HGX B300 servers make more sense.

GB300 NVL72 at a glance

GPUs
72x NVIDIA B300 (Blackwell Ultra) linked as one system
CPUs
36x NVIDIA Grace
GPU memory
About 21 TB per rack
Cooling
Liquid only
Power
About 130-140 kW per rack
Ballpark price
$8-8.6M per rack, with networking and installation

Is a rack right for you?

It fits the largest models, where 72 GPUs need to work as one. For most inference, HGX B300 servers use the same GPU, run air-cooled, and can be bought one at a time.

Vera Rubin, NVIDIA’s next generation, comes as racks and as 8-GPU servers. Early supply goes to the largest buyers. Tell us if you want to be in line.

What it takes to own one

  • A liquid-cooled site

    Few data centers can cool racks this dense, and their space goes fast.

  • Power and floor

    About 130-140 kW per rack, and a floor that can hold it.

  • Lead time

    Orders placed now arrive in about six months.

  • Compliance

    Expect a thorough review of the buyer, the site, and the use.

We guide. You decide.

  1. Scope it

    Tell us your workload, budget, and timeline. You get a plan and ballpark costs.

    One call

  2. We build it

    We compare vendors and data centers side by side. You pick, and we handle the rest in your name.

    60-90 days typically

  3. We run it

    Monitoring, repairs, and warranty claims, on an annual contract.

    Ongoing

What it costs

We take no cut of your hardware or data center. Brokers often earn a percentage of what you spend. We charge flat fees, so a better price only saves you money.

Paid to vendors, in your name

  • Hardware

    Servers, networking, and shipping. Paid to the vendor, with nothing added.

  • Colocation

    Space, power, and cooling, usually on a 3-year contract. Paid to the data center.

Paid to us, flat

  • Setup fee

    $25K for 1-7 servers. Half at signing, half when live. Custom pricing for 8 or more.

  • Management fee

    From $1K a month per 4 servers. Covers monitoring, repairs, and warranty claims.

Want a customer for the GPUs? We charge 2.5% of the contract, only if it signs.

Ballpark: one B300 server (8 GPUs)

The server
$550-650K
Shipping
$2,500
Data center
$4-5K a month
Our setup fee
$25K
Our management fee
$1K a month

A cluster also needs networking, about $50-70K per server.

Don’t want to pay for the hardware all at once?

  • Put in half yourself, and we can usually introduce a lender for the other half.
  • Lenders want to see cash or funding of 1.5x the hardware cost. For a $550K server, you put in $275K, the lender covers $275K, and you show $825K.

Tell us what you’re planning.

  • A call with our CTO about what you need
  • Ballpark costs and timelines for your budget
  • A straight answer if it’s not a fit

Prefer email? hello@amcompute.com

NVIDIA GB300 NVL72 racks: questions

How much does a GB300 NVL72 rack cost?
Ballpark $8-8.6M per rack, including networking and installation. The data center comes on top.
Can it be air-cooled?
No. It needs liquid cooling and a data center built for it.
How long until delivery?
Orders placed now arrive in about six months. The largest buyers are served first.
GB300 NVL72 or HGX B300?
Same GPU. The NVL72 links 72 of them for the largest workloads. HGX B300 links eight per server and fits far more data centers.

Further reading

Planning a rack? We’ll tell you what’s realistic.

Plan a deployment