How to deploy a B300 cluster, step by step
Nine steps and six counterparties before the first job runs. We line up all of them for a flat $25K, not a percentage of your project.
Six counterparties, or one
On your own
- Server vendor
- NVIDIA compliance
- Network vendor
- Data center
- Freight and insurer
- Installer
You deal with each of them directly.
- Six contracts, six contacts, six timelines.
- One missing form or a site without power holds everything.
- An infrastructure engineer, about $150K a year (American Compute).
With us
- Server vendor
- NVIDIA compliance
- Network vendor
- Data center
- Freight and insurer
- Installer
American Compute deals with each of them for you.
- One team lines up every party, in your name.
- No preferred vendors. You get the best price on the market right now.
- A flat $25K for 1-7 servers, not a percentage of the project.
Nine steps from quote to first job
Before the order
Size it
Servers, network, storage and power.
Who you deal with: Your team. Ballpark: Bill of materials builder.
Get quotes
Entity details, a credit application and NVIDIA’s end-use forms come before any firm quote.
Who you deal with: Vendors, NVIDIA compliance. Ballpark: Best price on the market now.
Order to delivery
Order
Weeks if in stock, five to six months from the factory.
Who you deal with: Server vendor. Ballpark: 20-50% deposit.
Sign a data center
High-density colocation, about 15 kW per server, usually on a 3-year contract.
Who you deal with: Data center. Ballpark: $240-325 per kW a month.
Ship and insure
Freight from the vendor, insured from the factory door.
Who you deal with: Freight and insurer. Ballpark: $2,500 per server.
Bring-up and run
Rack and network
Power, racking and an 800G network of switches, optics and cables.
Who you deal with: Installer, network vendor. Ballpark: $50-90K per server.
Burn in
Stress-test every GPU and the links between servers before you accept them.
Who you deal with: Installer. Ballpark: NVIDIA DCGM, NCCL tests.
Hand over
Drivers, CUDA, and Kubernetes or Slurm.
Who you deal with: Your team. Ballpark: NVIDIA GPU Operator.
Run it
Monitoring, repairs and warranty claims.
Who you deal with: Server vendor. Ballpark: For the life of the servers.
Where B300 projects stall
An order held for a form
Vendors won’t ship until NVIDIA’s end-use forms check out.
Servers with nowhere to go
Hardware that arrives before the site has power sits in storage, already paid for.
Lead times that slip
The cheapest factory orders can take five to six months.
Bad GPUs found late
Skip burn-in, and failures show up after you’ve accepted the servers.
What four B300 servers cost
Upfront
$2.6M
- Servers $2.2M
- Networking $220K
- Shipping and our setup $35K
- Install, storage and colo setup $109K
Each month
$24K
- Data center $17K
- Management $1K
- Parts, bandwidth and insurance $6K
Our fee
$25K
- Flat, for 1-7 servers. 8 or more quoted
- Not a commission or a percentage of the project
- 1% of this build alone would be $26K
Ballpark, October 2026, at $550K per server. Colocation at $280 per kW a month. After parts, bandwidth and insurance; before taxes and financing.
Plan your B300 deployment.
- A call with our CTO about what you need
- Ballpark costs and timelines for your budget
- A straight answer if it’s not a fit
Prefer email? hello@amcompute.com
Deployment questions
- How long does it take to deploy a B300 cluster?
- Smaller deployments usually go live in 60-90 days. Servers that ship within weeks cost more, and the cheapest factory orders can take five to six months.
- Can I deploy GPU servers myself?
- Yes, if you can line up the server vendor, NVIDIA’s compliance check, a network vendor, a data center, freight and insurance, and an installer, then handle repairs for years. One missing form or a site without power can hold the project for weeks.
- What paperwork do vendors ask for?
- The buying entity’s details, a credit application or a deposit, and NVIDIA’s end-use forms, which name the buyer, the site, and what the GPUs are for.
- Do I need InfiniBand?
- Not for one server. A cluster needs a fast network between servers, either InfiniBand or 800G Ethernet with RoCE, at about $50-90K per server.
- What do you charge to deploy it for me?
- A flat $25K setup for 1-7 servers, half at signing and half when live, quoted for 8 or more. Management from $1K a month per 4 servers. It is not a commission or a percentage of project cost. On a $2.6M four-server build, 1% alone would be $26K. We have no preferred vendors, so you get the best price on the market right now and pay the vendor directly.